Change order form

A one-page form that turns "can you also..." into a price, a date and a clear yes or no.

When to use it

  • The client asks for something that changes the cost, the time or the deliverables you agreed on.
  • The client wants to change something they already signed off.
  • Before you start the extra work, not after it's half done.
  • For small favors too: pick "No charge" so the favor is still on record.

Notes

  • Number change orders across the whole project, including declined ones. "Change order #4" shows the pattern without you having to point it out.
  • Keep it to one page. If the change needs more than that, it's a new phase and deserves its own quote.
  • A reply saying "approved" is usually enough of a record. Keep it in the same email thread as the form.
  • Set the "holds until" date 7 to 14 days out. A quote with no end date gets approved two months later at the old price.
  • Send it as a PDF, not an editable doc link.
  • This form is a template, not legal advice. If your agreement doesn't mention change orders, add a clause for next time, and for large amounts have a local lawyer look at it.